For anyone checking tree felling laws UK-wide, the key point is that licensing, protected-tree controls and wildlife law are separate checks. In England, the Forestry Act 1967 generally requires a felling licence unless an exemption applies, including felling no more than 5 cubic metres per calendar quarter, with no more than 2 cubic metres sold. Tree Preservation Orders and conservation-area controls under the Town and Country Planning Act 1990 can still apply, while the Wildlife and Countryside Act 1981 protects active wild bird nests. A client's instruction doesn't remove the contractor's potential liability under these laws.
Start with three separate permission checks
The chipper's booked, the driveway's sheeted and the client points at a mature ash: 'That one. Just take it down.' That's the moment to check the paperwork, not after the first gob cut. When people search tree felling laws UK, they're often hoping for one permission that covers everything. In England, there isn't one: the Forestry Act 1967, planning legislation and wildlife legislation address different things.
Start with the Forestry Commission's felling licence requirements under the Forestry Act 1967. Then check Tree Preservation Orders, usually called TPOs, and conservation-area status under the Town and Country Planning Act 1990. Finally, consider protected species under the Wildlife and Countryside Act 1981 and, where relevant, the Conservation of Habitats and Species Regulations 2017. Passing one check doesn't settle the others.
This article focuses on England. Wales also uses the Forestry Act 1967 licensing framework, administered by Natural Resources Wales, but check its current guidance rather than assuming English procedures transfer unchanged. Scotland operates under the Forestry and Land Management (Scotland) Act 2018, with Scottish Forestry administering felling permissions. Northern Ireland has separate forestry legislation, so don't use England's thresholds as a UK-wide permission slip.
Understand the 5 cubic metre quarterly exemption
Under the Forestry Act 1967, a commonly used exemption allows up to 5 cubic metres of timber to be felled in a calendar quarter, provided no more than 2 cubic metres is sold. The Forestry Commission's Tree felling: getting permission guidance explains how this works. Calendar quarters are January to March, April to June, July to September and October to December, not any three-month period you choose.
Five cubic metres isn't five trees. One substantial stem can use a large part of that allowance. Under the Forestry Commission's Tree felling: getting permission guidance, assess the standing timber volume before work, rather than guessing from the number of chipper loads afterwards. Get competent help if the estimate is close. A photograph of a brash pile won't establish how much timber was standing.
The Forestry Commission's guidance treats the allowance across the property, not as a fresh allowance for each contractor or each day's work. Ask what has already been felled that quarter and keep the answer with your estimate. Under the Forestry Act 1967 exemption, unused allowance doesn't build up for later quarters. Taking timber away as firewood doesn't make the felling disappear from the calculation.
Other Forestry Act 1967 exemptions include certain small-diameter trees and trees growing in gardens, orchards, churchyards or designated public open spaces, as explained in Forestry Commission guidance. Don't assume every grassed area beside a building is a garden, or that any public-access land is a designated public open space. Establish the actual land use and exemption. If none applies, obtain the licence before felling.
Treat TPOs and conservation areas separately
A garden tree may be exempt from Forestry Commission licensing yet still have a TPO. Under the Town and Country Planning Act 1990 and the Town and Country Planning (Tree Preservation) (England) Regulations 2012, protected-tree work generally needs the local planning authority's consent unless a specific exception applies. These controls cover more than felling, so describing the job as pruning isn't a way round them.
Check the council's records against the actual trees on site. A TPO can protect individual trees, groups, areas or woodland under the Town and Country Planning Act 1990. An online map is a useful starting point, but get the order and clarify anything uncertain with the tree officer. Match species, position and proposed work. A consent for one boundary tree isn't evidence for the one beside it.
For trees in conservation areas, section 211 of the Town and Country Planning Act 1990 generally requires six weeks' notice before work on trees over the relevant size threshold, unless an exemption applies. Under the 2012 tree preservation regulations, the usual threshold is a stem diameter exceeding 75 millimetres measured at 1.5 metres above ground, with a separate exception for certain thinning work.
Conservation-area notice isn't an ordinary application for TPO consent: the notice period gives the council an opportunity to protect the tree under the Town and Country Planning Act 1990. Keep evidence of valid notice, its receipt and the response. If a TPO already applies, use the TPO process instead. Ask the council to confirm the position before fixing a start date.
For the work sequence, use a tree surgery RAMS checklist alongside the permission pack.
Nesting season isn't a fixed legal window
March to August is a useful warning period for many nesting birds, not a legal calendar for switching protection on and off. Under section 1 of the Wildlife and Countryside Act 1981, intentionally damaging or destroying a wild bird's nest while it is in use or being built is generally an offence. Birds can nest outside the usual busy period, including in dense ivy that looks empty from below.
Build an appropriate nesting-bird check into the job before cutting, with further checks where conditions or timing change. Watch for repeated visits to one fork, birds carrying nesting material and alarm behaviour. Under the Wildlife and Countryside Act 1981, additional protections apply to Schedule 1 birds, including against intentional or reckless disturbance while nesting. Where identification or likely disturbance is uncertain, get competent ecological advice.
An active nest means stop and reassess the affected work, not ask the ground worker to move it into the next hedge. Protection under the Wildlife and Countryside Act 1981 isn't cancelled by a felling licence or the client's deadline. Establish a suitable stand-off and wait until the nest is no longer in use, with specialist advice where needed. There isn't one buffer distance that suits every species and operation.
Bats need a separate thought, particularly around cavities, splits and lifted bark. Under the Conservation of Habitats and Species Regulations 2017, damaging or destroying a bat breeding site or resting place can be an offence even when bats aren't present at that moment. A quick look from the lawn isn't enough to dismiss a suspected roost; pause and get appropriate ecological advice.
A client's instruction doesn't transfer your liability
'I own it' answers an ownership question, not a permission question. Under the Forestry Act 1967, the person felling without required authority can face prosecution, and an owner or other person causing or permitting the felling may also be liable. The Forestry Commission's Tree felling: getting permission guidance specifically warns that responsibility can involve the owner, agent, timber merchant or contractor. Don't treat someone else's confidence as evidence.
For protected trees, the Town and Country Planning Act 1990 creates offences around unauthorised work and causing or permitting prohibited work. A signed client instruction isn't a defence in itself. Ask for the actual consent, notice correspondence or evidence supporting an exemption. Check that it covers your tree and your operation. 'The previous builder sorted it' belongs in the same bin as 'the cable should be dead'.
Dangerous trees need proper judgement, not a convenient label. The Forestry Act 1967 includes an exemption for felling necessary to prevent danger, but decay or a client's anxiety doesn't automatically establish it. Under the 2012 tree preservation regulations, the urgent safety exception concerns work urgently necessary to remove an immediate risk of serious harm, with notice requirements. Keep photographs, inspection findings and reasons for the extent of work.
Unauthorised felling can leave more than a prosecution problem. The Forestry Act 1967 provides for restocking notices, while the Town and Country Planning Act 1990 includes replacement-tree duties in relevant protected-tree cases. A cleared site isn't necessarily the end of the matter. If the client refuses permission checks, leave the saw in the van and record why the work hasn't started.
Build a permission pack before the crew arrives
Keep one job file with a marked tree location, photographs, written scope and the owner's authority to instruct the work. Add the volume estimate and earlier felling record if relying on the Forestry Act 1967 quarterly exemption. Include the licence or reason for exemption, council correspondence and any ecological findings. The point is to make the decision traceable, not produce a fat folder nobody reads.
Make the permissions match the site briefing. Show the crew which stems stay, which come out and what triggers a stop. A bright paint mark is useful until two adjacent trees carry old marks from different visits. For the work sequence, use a tree surgery RAMS checklist alongside the permission pack. It's a practical way to keep authority to fell separate from how the job will be done safely.
Recheck after a delayed start, a changed scope or new wildlife activity. A client adding 'that little oak as well' changes the job, even if the chipper is already running. Permission records aren't a substitute for judgement on the day, and under the Forestry Act 1967 and protected-tree legislation, the actual felling must fit the licence, consent or exemption being relied on.
Questions we get asked
Can I cut down a tree in my own garden?
Trees growing in gardens are generally exempt from felling licensing under the Forestry Act 1967. However, the Town and Country Planning Act 1990 can still impose TPO or conservation-area controls, and the Wildlife and Countryside Act 1981 still protects active wild bird nests.
Does a dead tree need permission?
The Forestry Act 1967 includes an exemption for dead trees, but establish and record that the tree is dead. For TPO trees, the 2012 tree preservation regulations generally require five working days' written notice for dead-tree work, unless the urgent-risk exception applies. Confirm the applicable procedure with the council.
Can I fell trees in September?
September isn't an automatic all-clear: the Wildlife and Countryside Act 1981 protects nests while in use or being built, whatever the month. Check for nesting activity and complete the separate licensing and protected-tree checks before starting.
Will a felling licence let me remove a TPO tree?
Don't assume one document answers both questions. Forestry Commission guidance explains that applications involving TPO trees are referred to the local planning authority through the Forestry Act 1967 process. Confirm how the protected-tree controls have been addressed before work starts.
The short version
Before felling in England, check the Forestry Act 1967 licensing position, TPO and conservation-area controls under the Town and Country Planning Act 1990, and wildlife protection under the Wildlife and Countryside Act 1981.
Measure the timber rather than counting trees. Keep the evidence supporting any exemption, match permission to the actual work and stop if wildlife or scope changes. A client's instruction isn't permission, and the contractor can carry liability too.
If you need this written up properly for a real job, the paperwork is the easy part now.